City Centre Transit Terminal Infrastructure Renovation

In February 2020, the City Centre Transit Terminal will undergo a complete interior renovation that is expected to be completed by fall 2021.

During this construction period, the terminal will transform into a modernized space with improved accessibility and service for MiWay customers.

Customers will still be able to access the terminal during renovations and are encouraged to visit this page for project updates.

MiWay staff will continue to be onsite in order to serve you. Please look out for signage with temporary access points during these renovations.

Construction Details

The terminal was built in 1996 and is 23-years old. It requires facility upgrades to meet the growing and changing needs of our community.

Below is a summary of the renovation work and the expected construction timelines.

Please note: scheduling is subject to change.

 

Renovation Work Construction Begins
  • Demolition
  • North Entrance
  • Fares Booth
  • Upper-level flooring
Winter 2020
  • Staff washrooms
Spring 2020
  • Staircase
  • Elevator
  • Lower-level flooring
  • South Entrance (lower-level to Square One)
  • Supervisor Booth
  • Escalator
Fall 2020
  • Information Booth
Summer 2020